Hazel Storage Basin (CSO Racks 10 & 11)

Contractors continued construction of storage basin concrete screw pump slabs and installed 3 tipping buckets.  Operations building trusses were installed.  Diversion structure 3 began excavation after pilings were completed.  

Project Facts:

  • Capacity: 4.5 million gallons
  • Design to begin: 2016
  • Construction to begin: 2018
  • Construction to complete: 2020

 