Hello and welcome to the new Aqueduct Street Green Improvements construction page. 

The phone number to the field office has been installed and is ready for the residents with questions to leave messages. Please call (330) 252-8654 with your questions or comments if you cannot find the information you are looking for here.

Landscaping Updates 

July 2018 Photos 

June 2018 Photos

Important Update:

Green Infrastructure Guide 

Aqueduct March 30 Letter To Residents

March 23, 2018

Memorial Parkway to Morningside Drive

* The continuance with minor utility work below ground.  All traffic will be maintained.

* The continuance with the Green Infrastructure, all drives will be maintained.

* Begin the grading and placement of the walks and aprons along the west side of Aqueduct starting at Memorial Parkway and working toward West Market Street.  Please note that the drive entrances will be maintained up till the time that is required to form and pour the concrete aprons, once the aprons have been poured with concrete, there will be a 7 day cure period in that no vehicular access will be permitted into the drives until the concrete has obtained the proper strength.  Karvo Paving will provide notification to the residents that will be impacted. 

 

Morningside Drive to West Market Street

* The continuance with the utility work both above ground as well as below ground.  Road restrictions will apply.

March 3, 2018

Memorial Parkway to Morningside Drive

* The continuance with the paver installation, all residents should utilize their respective drives for parking both during and after hours.

* The continuance with minor utility work below ground.  All traffic will be maintained.

* The continuance with the Green Infrastructure, all drives will be maintained.

* Begin the grading and placement of the walks and aprons.  Please note that the drive entrances will be maintained up till the time that is required to form and pour the concrete aprons, once the aprons have been poured with concrete, there will be a 7 day cure period in that no vehicular access will be permitted into the drives until the concrete has obtained the proper strength.  Karvo Paving will provide notification to the residents that will be impacted. 

 

Morningside Drive to West Market Street

* The continuance with the utility work both above ground as well as below ground.  Road restrictions will apply.

February 1, 2018

Memorial Parkway to Morningside Drive

* The continuance with on street paver installation along the west side of Aqueduct Street, upon the installation of the pavers, all residents should utilize their respective drives for parking both during and after hours.

* The continuance with minor utility work both above ground as well as below ground.  All traffic will be maintained.

 Morningside Drive to West Market Street

* The continuance with minor utility work both above ground as well as below ground.  Temporary road restrictions will apply.

 

Jan 5, 2017

Memorial Parkway to Morningside Drive

* The installation with the on street pavers along the west side of Aqueduct Street, upon the installation of the pavers, all residents should utilize their respective drives for parking both during and after hours.

* Minor utility work above ground.  All traffic will be maintained.

  

Morningside Drive to West Market Street

* Minor utility work both above ground as well as below ground with temporary road restrictions.

Dec. 1, 2017

Karvo Paving will concentrate on building the on-street parking area between Memorial Parkway and Pasadena Avenue for the nexy two weeks.  Please note that the drive entrances along the west side of Aqueduct will experience periods of interruptions with no vehicle access.  Karvo Paving will provide advance notification to all residents that will be affected.  Overnight parking will continue along the east side of Aqueduct, we ask that all cars be moved off of Aqueduct by 7:30am Monday thru Friday so we can expedite the scheduled work.  

 

Nov. 17, 2017

Karvo Paving will concentrate the next two weeks with the following activities:

 

Memorial Parkway to Hillsdale Avenue

The week leading up to Thanksgiving: 

Karvo Paving anticipates placing another course of asphalt on Aqueduct, in doing so, we will end up with approximately 2 1/4" lip at the drive aprons until next year.  Please keep in mind that Karvo Paving will need all vehicles moved off of Aqueduct by 7am each day so we can obtain our goal of having all of the residents back in their drives by Thanksgiving.

 The week after Thanksgiving:

Karvo Paving anticipates beginning the underground stone storage behind the curb along the west side of Aqueduct, all drives will be maintained.

 Hillsdale Avenue to Morningside Drive

The week leading up to Thanksgiving: 

Karvo Paving anticipates paving Aqueduct, in doing so, we will end up with approximately 2 1/4" lip at the drive aprons until next year.  Please keep in mind that Karvo Paving will need all vehicles moved off of Aqueduct by 7am each day so we can obtain our goal of having all of the residents back in their drives by Thanksgiving.

 

Nov. 3, 2017

Karvo Paving will concentrate the month of November in obtaining asphalt pavement between Memorial Parkway and Morningside:

 Memorial Parkway to Hillsdale Avenue

* The week of November 6th - Installing the asphalt base course.

* The week of November 20th - Installing the asphalt Intermediate base course.

  Hillsdale Avenue to Morningside Drive

* The week of November 13th - Curb placement.

* The week of November 20th - Installing the asphalt Intermediate base course.

 Our goal for Aqueduct is to have the road paved and have the residents back in their drive by Thanksgiving.  

 

Oct 20, 2017

Please read this important notice!

CONCRETE CURB INSTALLATION 

"Starting next week (10-23-2017) Karvo will begin preparing for the concrete curb installation. You will see a yellow string line installed which the curb machine will follow. This will be taken down in the evening to allow access to your drive. Please do not disturb these pieces of equipment. On Wednesday we will install the curb on the east side of the roadway from Hillsdale to Memorial Parkway.

This process will continue on Thursday and Friday on the west side of the road from Memorial Parkway to Hillsdale. Once the curb is installed in front of your driveway, it will be approximately 2 weeks until the asphalt is placed and you can once again enter your driveway. Understand that all the above is weather dependent and minor changes may occur. We will try our best to keep you posted.


Please understand that you will be able to park in front of your house in the evening, and access the roadway from all areas (side streets and Memorial Parkway).


Please contact us if you have special needs so that we may accommodate you to the best of our ability."

Sept. 29, 2017

Karvo Paving will continue the next two weeks with the following improvements between Memorial Parkway and Morningside Drive:

* Continue with the full depth excavation, underdrain placement and stone base for the proposed roadway......Please note that during this procedure the drive entrances will be interrupted at times however, the drive entrances will be maintained with limestone 304 (gravel mix with fines).  Karvo Paving will provide notification to the residents which are impacted prior to the interruptions of their drive entrances. 

 * Continue the replacement of the active sanitary sewer laterals (house connection between the sewer main and the Right of Way).

 Sept. 15, 2017

 Karvo Paving will continue the next two weeks with the following improvements between Memorial Parkway and Morningside Drive:

* The continuance of the storm drainage installation which consist of new manholes, inlets and inlet connections.

* The continuance with the full width excavation curb to curb between Memorial Parkway and Morningside Drive.  Please note that during this procedure the drive entrances will be interrupted at times however, the drive entrances will be maintained with limestone 304 (gravel mix with fines).  Karvo Paving will provide notification to the residents which are impacted prior to the interruptions of their drive entrances. 

* Begin the replacement of every active sanitary sewer laterals (house connection between the sewer main and the Right of Way) starting at Memorial Parkway and working toward Morningside Drive. 

Sept. 7, 2017

Karvo Paving will continue the next two weeks with the following improvements between Memorial Parkway and Morningside Drive:

* The continuance of the storm drainage which consist of new manholes, inlets and inlet connections.

* Starting the full width excavation on or about September 12th, 2017 (pending weather) curb to curb at Memorial Parkway and working toward Morningside Drive.  Please note that during this procedure the drive entrances will be interrupted at times however, the drive entrances will be maintained with limestone 304 (gravel mix with fines).  Karvo Paving will provide notification to the residents which are impacted prior to the interruptions of their drive entrances. 

August 26, 2017

Karvo Paving will continue the next two weeks with the following improvements between Memorial Parkway and Morningside Drive:

* The continuance of replacing lead water services with copper within the right of way.

* The continuance of relocating the fire hydrants as needed for the improvements.

* Begin the installation of the storm drainage which consist of new manholes, inlets and inlet connections.

 Karvo Paving anticipates beginning the week of September 5th, 2017 with the full width excavation of the roadway (curb to curb) starting at Memorial Parkway and working toward Morningside Drive.  Please note that during this procedure the drive entrances will be interrupted at times however, the entrances will be maintained.

 August 21, 2017

The project consists of a new 12" water main being installed between Memorial Parkway and Edgerton Road along the west side of Aqueduct Street.  Prior to this week, the 12" water main was installed between Edgerton Road and Wellesley Avenue and is currently under going the necessary testing prior to connecting the water main into the system.

 The anticipated work for the next two weeks along Aqueduct Street:

* Continuance of the 12" water main installation between Wellesley Avenue and Memorial Parkway along the west side of Aqueduct Street.

* Continuance within the Right of Way of replacing lead water services with copper.

 

 

Please see the below links for the most recent letters we’ve sent to the neighborhood. 

Letter to Residents - Construction Meeting - August 2017

 Special Notice to Residents - July 2017

 

Hitorical Documents 

Overview PowerPoint

April 22 Meeting

Aqueduct Overview Flyer

Project Overview

This project consists of approximately 6,000 feet of roadway improvements between West Market Street and Memorial Parkway as well as various rehabilitation work on the existing sewers. Roadway improvements will include full-depth asphalt pavement reconstruction – complete with concrete curb, concrete sidewalks, concrete aprons, inlets, house drains, street trees, green infrastructure and a water main. Green infrastructure will include permeable unit pavement in the parking lane, rain gardens, bioretention, underground storage chambers, under-sidewalk storage, and a dry creek bed. PVC conduit lines will be installed down the length of the project for future “smart” infrastructure. Sewer rehabilitation work will include spot repairs and lining via cured-in-place pipe (CIPP).  One additional year of Green Infrastructure Operation and Maintenance.

 

 