Construction

Hazel Storage Basin (CSO Racks 10 & 11)

At the main basin, following the installment of anchors, slab on grade has been poured, rebar reinforcement is being installed and exterior walls being poured.  At diversion structure #1, mechanical and electrical systems were installed with existing piling removed.  Site was backfilled and graded.  At diversion structure #2 mechanical and electrical systems were installed with existing piling being removed in July.   Dewatering of all sites will remain ongoing.

Project Facts:

  • Capacity: 4.5 million gallons
  • Design to begin: 2016
  • Construction to begin: 2018
  • Construction to complete: 2020

 