Construction

Ohio Canal Interceptor Tunnel (OCIT-3)

This site sits between West Exchange Street and West Cedar Street along the Ohio & Erie Canal. It marks the southern most point of the Ohio Canal Interceptor Tunnel. A 45-foot diameter drop shaft is being constructed that will connect with the tunnel at a depth of 166 feet.

In November, the contractor completed construction of the roof slab and started work on the flow channel.  Additionally, they have started chipping through the secant piles at the OCIT-3 Drop Shaft in preparation for installation of the Rack 16 Consolidation Sewer.  The Contractor completed excavation, and installed the flume pipe at the Rack 17 Diversion Structure. The base slab was completed at the end of the month.

 

December 2018 Photos

 

November 2018 Photos

 

October 2018 Photos

 

September 2018 Photos

August 2018 Photos

July 2018 Photos

June 2018 Photos

May 2018 Photos

April 2018 Photos

March 2018 Photos

February 2018 Photos

January 2018 Photos

November 2017 Photos

October 2017 Photos

September 2017 Photos

August 2017 Photos

July 2017 Photos

June 2017 Photos

 May 2017 Photos

April 2017 Photos

March 2017 Photos

February 2017 Photos

January 2017 Photos

November 2016 Photos

October 2016 Photos

August 2016 Photos

July 2016 Photos

June 2016 Photos

May 2016 Photos

March 2016 Photo

Back to Construction Listing