Construction Map

WRF BioCEPT

The midspan effluent channel, should be poured Monday which will conclude pours for walkway deck. Once lower wall and slab are cured, shoring will be removed, and moved to the west side to continue. Pipe gallery walls have been completed and stripped. Currently, installing air piping, continuing with NPW line installation, and RAS piping in that area before putting roof on pipe gallery. N. baffle wall walkway completed, once cured everything will be stripped, then begin forming and placing walkways. This week will begin setting roof trusses. They will start in the middle of the building and work east then they will return to the middle and work west. Once trusses are set, they will install metal decking.

BioCEPT

Headworks - Main Outfall

The live stream cameras you see below are part of the Headworks project to upgrade to the Main Outfall to provide 280 MGD capacity to the Water Reclamation Facility. The project will include replacement of the Influent Screening Building, Grit Removal and Grit Load-out Buildings, Detritus Tanks, and associated channels and gates. The existing Main Outfall from the east side of the bridge to the new Headworks will be rebuilt similar to the design of the current Main Outfall (MO) project. 

Headworks

November 2021 Photos

August 2021 Photos

July 2021 Photos

March 2021 Photos

December 2020 Photos

November 2020 Photos

October 2020 Photos

September 2020 Photos

August 2020 Photos

July 2020 Photos

June 2020 Photos

May 2020 Photos

April 2020 Photos

March 2020 Photos

February 2020 Photos 

January 2020 Photos 

December 2019 Photos

November 2019 Photos

October 2019 Photos

September 2019 Photos 

August 2019 Photos 

July 2019 Photos 

Back to Construction Listing