Aqueduct Street Green Improvements (Phase I)

This project consists of approximately 6,000 feet of roadway improvements between West Market Street and Memorial Parkway as well as various rehabilitation work on the existing sewers. Roadway improvements will include full-depth asphalt pavement reconstruction – complete with concrete curb, concrete sidewalks, concrete aprons, inlets, house drains, street trees, green infrastructure and a water main.

Green infrastructure will include permeable unit pavement in the parking lane, rain gardens, bioretention, underground storage chambers, under-sidewalk storage, and a dry creek bed. PVC conduit lines will be installed down the length of the project for future “smart” infrastructure. Sewer rehabilitation work will include spot repairs and lining via cured-in-place pipe (CIPP).  One additional year of Green Infrastructure Operation and Maintenance.